The company that is putting ceaseless effort to lay more advanced foundation for human being is Byucksan Engineering
 
 
   
 
Water Supply
Sewage, Waste Water and Rainwater
   
   
 
 
 
   

   
Sewage, Waste Water andRainwater
 
 
Extension of Seongnam Sewage Treatment Plant Stage 2
 
Scope: Basic plan, enforcement design and Total Responsibility Supervision
Scale: Sewage treatment capacity of 40,000m3/day (Collection Pipe: L=6.1km, enforcement design)
Capacity
  Existing Facility: 395,000m3
Extended Facility: 40,000m3
Treatment Method: Biological process for nitrogen and phosphorus (A2/O technique)
Sewage Intercepting Pipe: Dual-walled PE pipe with D=900mm and L=6.082.9m
   
Extension of Sewage Treatment Facility in Jecheon
 
Scope: Basic/ enforcement design, Total Responsibility Supervision
Sewage Treatment Plant
Facility Capacity: 70,000m3/day
Sewage Treatment Method: Conventional activated sludge process
Sewage Intercepting Pipe
Hasocheon Line (Size: D=400-500mm, Length: 3,232m (total of 4,363m))
Jangpyeongcheon Line (Size: D=450-600mm, Length: 4,789m)
Wangam Industrial Complex Line (Size: D=450-600mm, Length: 4,789m)
Night Soil Sending Line (Size: D=STS D200, Length: 4,213m)
   
Construction Project of Yakmok Sewage Treatment Plant
 
Scope: Basic/ enforcement design, Total Responsibility Supervision
Sewage Treatment Plant
Facility Capacity: 20,000m3/day
Sewage Treatment Method: Activated sludge process (A2/0 technique)
Sewage Intercepting Pipe
Line A (Size: D=400-1,100mm, Length: 3,18km)
Line B (Size: D=400-700mm, Length: 2.02km)
Line B-1 (Size: D=400mm, Length: 0.68km)
Line C (Size: D=300-600mm, Length: 1.92km)
Line D (Size: D=300-500mm, Length: 0.70km)
Line E (Size: D=400-600mm, Length: 0.69km)
   
Sewage Treatment Facility in Hyeon-ri, Gapyeong-gun
 
Scope : Basic plan
Scale
Sewage Treatment Plant: 5,100m3/day, Arterial Drainage Pipe: 10.33km
2 pumping stations
Treatment Method
Water Treatment: K-intermittent decanted extended aeration process (KIDEA)
Sludge Treatment: Mechanical condensation + dehydration -> composting
   
Seongnam Sewage Treatment Plant, Advanced treatment & 3rd Extension
 
Customer : Seongnam-Si
Schedule : Apr,2003 ~ Dec,2004
overview
Advanced Treatment Capacity : 220,000m3/day
Extension Capacity : 25,000m3/day
Advanced Treatment : A2O(NPR) Process
Scope :
Basic Design
Detailed Design
   
Jeollabuk-Do Sewage Treatment Plant
 
Customer : Jeollabuk-Do
Schedule : Oct,2000 ~ Aug,2004
Overview :
Saemangeum Reclaimed Area (Saemangeum Tideland Reclamation)
19 New Sewage Treatment Plant & Expansion
O & M of Existing Plants & New Plants
Scope :
Master Plan
Basic Design
Detailed Design