Major Achievements |
|
|
|
|
| |
| |
 |
|
The
company that is putting ceaseless effort to lay more advanced
foundation for human being is Byucksan Engineering |
|
|
|
 |
|
|
| |
| |
 |
|
|
| |
|
|
|
|
| |
|
|
 |
Metropolitan
Waterworks Construction Project in Buan Dam System |
| |
|
Scope: Basic design, enforcement design,
Total Responsibility Supervision |
 |
Scale: 1 purification plant (87,000 ton/day),
3 pressurizing plants Water supply pipeline
of 104.2km (D900-200) |
 |
Water Supply Target Regions: Buan, Gochang,
Byeonsan Beach, Saemangeum Reclaimed Area
(Saemangeum Tideland Reclaimation) |
| |
|
|
|
|
 |
Metropolitan
Waterworks Project (stage 2) in Namgang Dam System |
| |
|
Scope : Research of appropriateness, basic
plan, enforcement plan |
 |
Capacity: 95,000m3/day |
 |
Water Supply Target Regions: Tongyeong,
Geoje, Sacheon, Jinju, Goseong, Namhae,
Hadong |
 |
Construction Zone 1: Purification
plant with capacity of 235,000m3 (Facility
2: 95,000m3)
1 set of canal/ water pipe within the zone |
 |
Construction Zone 2: Water
intake plant with capacity of 235,000m3
(Facility 2: 95,000m3) |
| |
Diameter of Canal Pipe: 1,500mm/
Extension: 13,425m
Diameter of Water Pipe: 1,100 ~ 250mm/ Extension:
111,854,
Diameter of Water Supply Tunnel: 2.5m/ Extension:
471m
Capacity of Control Basin: 6,914m3 |
|
| |
|
|
|
|
|