Business Introduction
  Major Achievements
  Structural
  - Road and airport
  - Railroad and urban train
  - Urban planning
  - Foundation and
    underground space

  Water & Sewerline
  Environmental Service
  Oil, Gas & Chemical
  Building
  Energy
 
   
   
   
   
     
 
    Major Achievements
 
 
 
The company that is putting ceaseless effort to lay more advanced foundation for human being is Byucksan Engineering


 
 
   
 
Road and Airport
Railroad and Urban train
Urban planning
Foundation and Underground space
 
 
 
   

   
Foundation and Underground space
 
 
U-2 Crude Oil Transshipment Station
 
Research and design
 
Details of Project
1) Investigation on the prearranged site of underground cave for crude oil storage facility
2) Ground plan design in connection with the existing facilities
   
Sin-Uljin Branch of Nuclear Power Plant
 
Scope : Preliminary research
 
Details of Project
1) Site arrangement and scope of the prearranged site designation for nuclear power plant
2) To be utilized as design data in future construction projects
   
Sin-Wolseong (Bonggil) Branch of Nuclear Power Plant
 
Scope : Detailed geological research
 
Details of Project
1) Examining possibility of succeeding unit construction through expansion of the site adjacent to the
     nuclear power plant
2) Preparing data to obtain permit from government offices, such as site investigation report, etc.
     required in promotion of construction operations
   
Yeonggwang Nuclear Power Plant Unit 5 & 6
 
Scope : Additional geological research
 
Details of Project
1) Examining possibility of succeeding unit construction through expansion of the site adjacent to the
     nuclear power plant
2) Preparing site research report required in promotion of construction operations
   
Depth Drainage Way Design for Sin-Wolseong Unit 1 & 2
 
Scope : Preliminary geological research
 
Details of Project
1) Geological research in the prearranged zone for depth drainage structure construction
2) Selecting route by considering various geological conditions and engineering characteristics of the
     structure
   
Foundation Reinforcement Construction in Mungyeong Region
 
Basic and enforcement design
 
Details of Project
1) Foundation stability assessment through mineral extraction
2) Determining the necessity of precision research by administering great-sphere research and
     detailed research
   
Construction Project of Deep Water Intake and Drainage Structure for Sin-Gori Unit 1 & 2
 
Scope: Supervision
Schedule: Oct. 2005 ~ Aug. 2008
Customer: Korea Hydro & Nuclear Power
Overview: Construction of cooling water drainage tunnel for nuclear plant unit 1 & 2
Tunnel Length per Unit: 500m
   
Environmental Restoration Project for Construction Site of I-Park in Dalcheon, Ulsan
 
Scope: Construction
Schedule: Jul. 2005 ~ Dec. 2006
Customer: Hyundai Development Company
Overview: Environmental restoration for the polluted soil
   
Ground Stability Investigation in Buk-myeon District of Jeongseon
 
Scope: Precision research
Schedule: Feb. 2006 ~ Sep. 2006
Customer: Coal Industry Promotion Board
Overview: Research on ground settlement caused by mining in dead pit as a part of mine pollution control project